NW Redevelopment Plans and Schedule
The Northwest Campus was approved for a $311 Million redevelopment project. What you see on campus currently is the beginning of this redevelopment.
Our hope is that this module will provide you information to best access the Northwest campus with ease!
Below is a rendering of what the campus layout will be in 2025.
Here’s a timeline of major portions of construction and demolition arranged by the years in which they begin:
— 2022-2023 –
- August 2023 - Demolition of WFAB
- September 2023 - Demolition of WSTU
- October 2023 - Demolition of WTLO
- October 2023 - Moves from WCTS and NW05 into NW01 will take place
- October to March 2025 – Construction of Building 3
- October to May 2025 – Construction of Building 4
- May to January 2026 – Reskinning of WACB
- July to October 2025 – Demolition of WCTS
For more information about the redevelopment visit the Northwest Campus: Campus Re-Development – Tarrant County College Bond Project (tccd.edu).